How to Install Tri Iso Super 9 for Floor

Installing Tri-iso Super 9 for Floor application floor1

Floor application requires a batten frame to be built. This is needed as the product requires a 20mm air gap. This is an important factor so to ensure any heat exchange is made through radiation. Then staple the insulation product using corrosive resistant staples at 50cm intervals onto the battens & make sure the overlap is between 5cm and 10cm and taped. Then attach the 2nd layer of battens directly above the 1st layer of battens. Then attach the flooring.

floor2 floor3 